House updates




The new Kitchen windows are in.
The new structural Beam in the kitchen is in.
HVAC is close to being complete.
Sub floor in bathroom is finished...plumbers are installing tub tomorrow.
Electricians are in and should be complete by next week.
New plumbing installed.
New concrete poured in basement.
Next week plumbers, electricians and Hvac should all be complete.
Insulators are due to start the Monday we are back from Indiana.
Framing is not complete but Dave is working diligently when he can...he pulled some late nights this week.
Off to Indiana tomorrow - Looking forward to it and know that when we're back -BUSY time ahead...